Delivery

Jobs

14 active jobs · the full solar lifecycle, survey to handover
Live demo · sample data

All jobs

click a job to open it
All stages
JobCustomerTypeSystemStageDNOEngineerValueDue
J-1042A. Kelly
Strabane
Solar + Battery6.4kWp · 10.4kWhInstallG99 approvedLiam B£11,240Today
J-1039M. Gallagher
Coleraine
Solar PV4.0kWpMCS handoverG98 notifiedLiam B£6,480MID in 6d
J-1044Bradley Farm
Garvagh
Solar + Battery12.0kWp · 20.8kWhProcurementG99 approvedSean G£24,9002 Sep
J-1047K. Doherty
Limavady
Solar + EV5.6kWp · 7kW chargerCommissionG98 notifiedDeclan M£9,180Tomorrow
J-1051Omagh GAA
Omagh
Commercial Solar29.9kWpDNO / G99G99 overdueCiaran D£38,600G99 pending
J-1053S. Friel
Derry
Heat pump (ASHP)11kW ASHPSurveyn/aAoife O’K£8,9005 Sep
J-1049P. Toner
Dungiven
Solar + Battery5.2kWp · 5.2kWhDesign & quoteG98Ronan K£9,950Quote sent
J-1036R. Hamilton
Ballymoney
Solar PV3.68kWpSurveyn/aAoife O’K£5,8508 Sep
J-1042Install

Aidan Kelly — Solar + Battery

Strabane, BT82 · 07701 ••• ••• · aidan.kelly@… · FB lead · Niamh McLaughlin
Value
£11,240
Margin
38.7%
Survey
28 Jul
Design & quote
30 Jul
DNO / G99
2 Aug
Procurement
12 Aug
5
Install
Today
6
Commission
7
MCS handover
▶ Currently: install day 1 of 2 — Liam Bradley + Sean Gallagher
System
Array16 × 400W panels — 6.4kWp
InverterHybrid 5.0kW (1 string, 16 modules)
Battery2 × 5.2kWh BESS — 10.4kWh
Est. generation5,720 kWh/yr · SEG eligible
RoofSouth-west, 35° pitch, no shading
Job photos · 4
Roof — before
Array layout
Inverter + battery
Consumer unit
Compliance & certificates
DNO — G99 approval
the DNO · 2 Aug
done
EIC (BS 7671)
Due on commissioning
due
Commissioning (BS EN 62446)
Due tomorrow
due
MCS certificate
After commissioning
MID registration
≤10 working days
RECC + handover pack
On handover
Stock allocated
16× 440W mono panel
PNL-440 · Van — Sean G
1× Hybrid inverter 5.0kW
INV-HYB-5.0 · Warehouse
2× Battery module 5.2kWh
BAT-5.2 · Warehouse
12× Mounting rail (2.1m)
MNT-RAIL · Van — Liam B
40× DC cable 6mm²
CAB-DC-6 · Van — Liam B
Job costing
Equipment (panels, inverter, battery)£4,820
Consumables + mounting£640
Labour (2 installers × 2 days)£980
Scaffolding (sub-contract)£450
Total cost£6,890
Gross margin£4,350 · 38.7%